Ozark Pipeline Upgrade Planned Beneath Mississippi River
11/11/2015
Canadian company Enbridge will make $17.3 million in improvements to its Ozark Pipeline along a 4,000-foot segment that runs beneath the Mississippi River into north St. Louis. The work is scheduled for completion in 2016.
Crews will bore under the river, welding 22-inch steel pipe together on the Missouri side, before pulling it through a new tunnel. The 435-mile Ozark Pipeline carries up to 215,000 bpd of oil from Oklahoma through Missouri, en route to the Wood River, IL refinery, Enbridge said.
Missouri Gov. Jay Nixon, touting the project for creating jobs said the effort “represents another example of how Missouri is leading the way toward greater North American energy independence from right here in the heartland.”
Related News
Related News
Sign up to Receive Our Newsletter
- Phillips 66 to Shut LA Oil Refinery, Ending Major Gasoline Output Amid Supply Concerns
- FERC Sides with Williams in Texas-Louisiana Pipeline Dispute with Energy Transfer
- U.S. Appeals Court Blocks Kinder Morgan’s Tennessee Pipeline Permits
- ConocoPhillips Eyes Sale of $1 Billion Permian Assets Amid Marathon Acquisition
- Valero Considers All Options, Including Sale, for California Refineries Amid Regulatory Pressure
- U.S. Appeals Court Blocks Kinder Morgan’s Tennessee Pipeline Permits
- Malaysia’s Oil Exports to China Surge Amid Broader Import Decline
- U.S. LNG Export Growth Faces Uncertainty as Trump’s Tariff Proposal Looms, Analysts Say
- Marathon Oil to Lay Off Over 500 Texas Workers Ahead of ConocoPhillips Merger
- Valero Considers All Options, Including Sale, for California Refineries Amid Regulatory Pressure
Pipeline Project Spotlight
Owner:
East African Crude Oil Pipeline Company
Project:
East African Crude Oil Pipeline (EACOP)
Type:
TotalEnergies in discussions with a Chinese company after Russian supplier Chelpipe was hit by sanctions.
Length:
902 miles (1,443 km)
Capacity:
200,000 b/d
Start:
2022
Completion:
2025