North Dakota Regulators Investigating Minnesota Contractor

BISMARCK, N.D. (AP) — A Minnesota contractor that damaged a natural gas pipeline in North Dakota last week has a history of striking pipelines.
The damage caused the release of 126,000 gallons of natural gas liquids and shut down a gas processing plant for three days.
State regulators who recently fined Carstensen Contracting of Pipestone, Minnesota, in another incident are investigating.
President Brad Carstensen says the company took the necessary steps to locate underground pipelines, and is still investigating what happened.
The Bismarck Tribune reports it’s at least the second gas pipeline the contractor has damaged in North Dakota while installing water pipelines. In addition, city leaders in Fort Dodge, Iowa, parted ways with Carstensen last summer after the contractor hit 20 underground utility lines while working on a sewer project.
Related News
Related News

- Enbridge Plans 86-Mile Pipeline Expansion, Bringing 850 Workers to Northern B.C.
- Intensity, Rainbow Energy to Build 344-Mile Gas Pipeline Across North Dakota
- Enbridge Sees High Demand to Expand 593-Mile Canada-to-U.S. Gulf Oil Pipeline
- Energy Transfer to Build $5.3 Billion Permian Gas Pipeline to Supply Southwest
- Strike Pioneers First-of-Its-Kind Pipe-in-Pipe Installation on Gulf Coast with Enbridge
- A Systematic Approach To Ensuring Pipeline Integrity
- 275-Mile Texas-to-Oklahoma Gas Pipeline Enters Open Season
- LNG Canada Start-Up Fails to Lift Gas Prices Amid Supply Glut
- Enbridge Sees High Demand to Expand 593-Mile Canada-to-U.S. Gulf Oil Pipeline
- Strike Pioneers First-of-Its-Kind Pipe-in-Pipe Installation on Gulf Coast with Enbridge
Comments