Millennium Pipeline's Eastern System Upgrade Project Approved
11/30/2017

FERC has approved Millennium Pipeline’s Eastern System Upgrade Project, which includes the construction of the following:
- An approximately 7.8-mile-long, 30- and 36-inch-diameter pipeline loop in Orange County, New York (Huguenot Loop)
- A new compressor station in Sullivan County, New York (Highland Compressor Station), with one 22,400 horsepower Solar Titan 130E gas-fired turbine compressor unit
- A new 22,400 horsepower Solar Titan gas-fired turbine compressor unit at the existing Hancock Compressor Station in Delaware County, New York
- Modifications to the existing Ramapo Meter and Regulator Station in Rockland County, New York
- Modifications to the Wagoner Interconnect in Orange County, New York
- Additional pipeline appurtenant facilities at the existing Huguenot and Westtown Meter and Regulating Stations in Orange County, New York
- An alternate interconnect to the 16-inch-diameter Valley Lateral5 at milepost 7.6 of the Huguenot Loop
Once finished, the Eastern Upgrade Project will add 223 MMcf/d of capacity along Millennium’s system in New York.
The project is expected to begin operations Fall 2018.
Related News
Related News
Sign up to Receive Our Newsletter

- Enbridge Plans 86-Mile Pipeline Expansion, Bringing 850 Workers to Northern B.C.
- Intensity, Rainbow Energy to Build 344-Mile Gas Pipeline Across North Dakota
- U.S. Moves to Block Enterprise Products’ Exports to China Over Security Risk
- Court Ruling Allows MVP’s $500 Million Southgate Pipeline Extension to Proceed
- 208-Mile Mississippi-to-Alabama Gas Pipeline Moves Into FERC Review
- U.S. Pipeline Expansion to Add 99 Bcf/d, Mostly for LNG Export, Report Finds
- A Systematic Approach To Ensuring Pipeline Integrity
- 275-Mile Texas-to-Oklahoma Gas Pipeline Enters Open Season
- LNG Canada Start-Up Fails to Lift Gas Prices Amid Supply Glut
- Kinder Morgan Gas Volumes Climb as Power, LNG Demand Boost Pipeline Business
Pipeline Project Spotlight
Owner:
East African Crude Oil Pipeline Company
Project:
East African Crude Oil Pipeline (EACOP)
Type:
TotalEnergies in discussions with a Chinese company after Russian supplier Chelpipe was hit by sanctions.
Length:
902 miles (1,443 km)
Capacity:
200,000 b/d
Start:
2022
Completion:
2025
Comments