Utility: Weight of Fill Material Caused Gas Pipeline Fire
1/16/2018
ORION TOWNSHIP, Mich. (AP) — A Michigan utility says the weight of 21 feet of fill material was responsible for a November gas line rupture and massive fire in Oakland County’s Orion Township.
Jackson-based Consumers Energy says Monday in a statement that the weight of the material “stressed the pipeline and caused it to sag due to the compressibility of the supporting organic soil layer.”
The utility says the material was added by a third party.
The fire started Nov. 20 on vacant land about 30 miles north of Detroit. The blaze eventually burned itself out. No injuries were reported.
Oakland County Sheriff Michael Bouchard said the office’s phone lines, including 911, were down as a result of the fire.
Related News
Related News
Sign up to Receive Our Newsletter
- Phillips 66 to Shut LA Oil Refinery, Ending Major Gasoline Output Amid Supply Concerns
- FERC Sides with Williams in Texas-Louisiana Pipeline Dispute with Energy Transfer
- U.S. Appeals Court Blocks Kinder Morgan’s Tennessee Pipeline Permits
- ConocoPhillips Eyes Sale of $1 Billion Permian Assets Amid Marathon Acquisition
- Valero Considers All Options, Including Sale, for California Refineries Amid Regulatory Pressure
- U.S. Appeals Court Blocks Kinder Morgan’s Tennessee Pipeline Permits
- Malaysia’s Oil Exports to China Surge Amid Broader Import Decline
- U.S. LNG Export Growth Faces Uncertainty as Trump’s Tariff Proposal Looms, Analysts Say
- Marathon Oil to Lay Off Over 500 Texas Workers Ahead of ConocoPhillips Merger
- Valero Considers All Options, Including Sale, for California Refineries Amid Regulatory Pressure
Pipeline Project Spotlight
Owner:
East African Crude Oil Pipeline Company
Project:
East African Crude Oil Pipeline (EACOP)
Type:
TotalEnergies in discussions with a Chinese company after Russian supplier Chelpipe was hit by sanctions.
Length:
902 miles (1,443 km)
Capacity:
200,000 b/d
Start:
2022
Completion:
2025
Comments