Rover Pipeline’s Full Mainline B Goes into Full Service
Energy Transfer Partners today that Rover Pipeline received approval from the Federal Energy Regulatory Commission (FERC) to begin service of the Supply Connector B and full Mainline B pipeline segments.
Service to the Market Zone north segment of the pipeline, with deliveries into the Union Gas Dawn Storage Hub in Ontario, Canada, will begin by way of the Vector Pipeline Connection in Michigan.
This latest approval allows for 100% of Rover’s mainline capacity, 3.25 Bcf/d of natural gas, to be placed into service.
The FERC decision, however, did not allow gas to flow on two key laterals the – Burgettstown and the Majorsville – connecting to supply areas.
Rover transports natural gas from the Marcellus and Utica Shale production areas to markets across the United States, as well as into the Union Gas Dawn Storage Hub for redistribution back into the United States or into the Canadian market.
Related News
Related News

- Enbridge Plans 86-Mile Pipeline Expansion, Bringing 850 Workers to Northern B.C.
- Intensity, Rainbow Energy to Build 344-Mile Gas Pipeline Across North Dakota
- U.S. Moves to Block Enterprise Products’ Exports to China Over Security Risk
- Court Ruling Allows MVP’s $500 Million Southgate Pipeline Extension to Proceed
- 208-Mile Mississippi-to-Alabama Gas Pipeline Moves Into FERC Review
- U.S. Pipeline Expansion to Add 99 Bcf/d, Mostly for LNG Export, Report Finds
- A Systematic Approach To Ensuring Pipeline Integrity
- 275-Mile Texas-to-Oklahoma Gas Pipeline Enters Open Season
- LNG Canada Start-Up Fails to Lift Gas Prices Amid Supply Glut
- Kinder Morgan Gas Volumes Climb as Power, LNG Demand Boost Pipeline Business
Comments