Crude Oil Service to Begin on Epic NGL Pipeline in 2019
SAN ANTONIO – Epic Midstream Holdings obtained all required approvals for its subsidiary Epic Crude Oil Pipeline, through a lease arrangement, to begin crude oil service on a portion of the Epic NGL Pipeline, once construction is completed in the third quarter of 2019.
Because of high customer demand for crude oil transportation, EPIC made the decision to use the third and final phase of its Epic NGL Pipeline from Crane to Corpus Christi, Texas, for crude oil service while its crude oil pipeline and NGL fractionator remain under construction. The NGL Pipeline will convert back to NGL service by January 2020.
The portion of the NGL line being placed into crude service will originate in Crane with an additional injection point in Wink, Texas, and will have multiple terminal and refinery connections in Corpus Christi and Ingleside. The 24-inch NGL line will have a capacity of 400,000 bpd for its interim crude service. The construction of the final phase of the EPIC NGL Pipeline is progressing on time with three contractors working on the project over five spreads of the pipeline path.
Because of its commercial success, EPIC will upsize its pipeline from a 24-inch line to a 30-inch line, expanding its Permian Basin capacity to 600,000 bpd. With the installation of additional pumps and storage, EPIC can increase the 30-inch capacity to 900,000 bpd.
The EPIC Crude Oil Pipeline will run side-by-side with the EPIC NGL Pipeline with the crude line expected to be completed by January 2020.
Related News
Related News
- Trump Aims to Revive 1,200-Mile Keystone XL Pipeline Despite Major Challenges
- Valero Considers All Options, Including Sale, for California Refineries Amid Regulatory Pressure
- ConocoPhillips Eyes Sale of $1 Billion Permian Assets Amid Marathon Acquisition
- ONEOK Agrees to Sell Interstate Gas Pipelines to DT Midstream for $1.2 Billion
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- U.S. LNG Export Growth Faces Uncertainty as Trump’s Tariff Proposal Looms, Analysts Say
- Tullow Oil on Track to Deliver $600 Million Free Cash Flow Over Next 2 Years
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- GOP Lawmakers Slam New York for Blocking $500 Million Pipeline Project
- Texas Oil Company Challenges $250 Million Insurance Collateral Demand for Pipeline, Offshore Operations
Comments