Mountain Valley Pipeline Project to Be 70% Complete by Year-End
12/13/2018
PITTSBURGH – Mountain Valley Pipeline (MVP) officials said the company remains on target for the $4.6 billion project in fully in-service in the fourth quarter of 2019.
Mountain Valley expects to have 70% of the MVP project complete by year-end, which includes the welding of nearly 58% of the pipeline and the ongoing construction work of all compressor stations and interconnects that are expected to be complete by February.
Most recently, MVP construction crews have focused on stabilizing the right-of-way for the winter season.
“Despite various setbacks and unprecedented weather conditions, we have made substantial progress this year,” said Chief Operating Officer Diana Charletta, of Equitrans Midstream Corporation.
Related News
Related News
Sign up to Receive Our Newsletter
- Williams' $1 Billion Gas Pipeline Blocked by U.S. Appeals Court, Derailing Five-State Project
- Texas Waha Hub Gas Prices Plunge to Record Lows, Hit Negative Territory
- Williams Begins Louisiana Pipeline Construction Despite Ongoing Legal Dispute with Energy Transfer
- U.S. Buys Nearly 5 Million Barrels of Oil for Emergency Stockpile
- U.S. Appeals Court Strikes Down Controversial Biden Pipeline Safety Rules
- Report: Houston Region Poised to Become a Global Clean Hydrogen Hub
- Exxon Mobil to Start Gas Reserve Seismic Surveys in Greece
- LaPorte, Texas, Issues Shelter in Place After Altivia Plant Leaks Toxic Gas
- Texas Startup Endeavors Again to Build First Major U.S. Oil Refinery Since 1977
- Second Gas Pipeline Rupture in Texas’ Reeves County Raises Environmental Concerns
Pipeline Project Spotlight
Owner:
East African Crude Oil Pipeline Company
Project:
East African Crude Oil Pipeline (EACOP)
Type:
TotalEnergies in discussions with a Chinese company after Russian supplier Chelpipe was hit by sanctions.
Length:
902 miles (1,443 km)
Capacity:
200,000 b/d
Start:
2022
Completion:
2025
Comments