Cheniere Announces Substantial Completion of Train 5 at the Sabine Pass Liquefaction Project
HOUSTON - Cheniere Energy Partners, L.P. (Cheniere) announced today that Substantial Completion of Train 5 of the Sabine Pass Liquefaction (SPL) Project in Cameron Parish, Louisiana was achieved on March 7, 2019. Commissioning has been completed and Cheniere's EPC partner Bechtel has turned over care, custody, and control of Train 5 to Cheniere.

Under sale and purchase agreements (SPAs) with Centrica plc and Total Gas & Power North America, Inc., the date of first commercial delivery is expected to occur in August 2019, upon which the term of each of these SPAs commences.
Cheniere and Bechtel have now declared Substantial Completion on five liquefaction trains at the SPL Project ahead of each train’s guaranteed completion date and within project budgets. With the achievement of Substantial Completion, financial results of LNG sales from Train 5 going forward will be reflected in the statement of operations of Cheniere and its applicable affiliates.
Related News
Related News

- 1,000-Mile Pipeline Exit Plan by Hope Gas Alarms West Virginia Producers
- Valero Plans to Shut California Refinery, Takes $1.1 Billion Hit
- Three Killed, Two Injured in Accident at LNG Construction Site in Texas
- Greenpeace Ordered to Pay $667 Million to Energy Transfer Over Dakota Access Pipeline Protests
- Boardwalk’s Texas Gas Launches Open Season for 2 Bcf/d Marcellus-to-Louisiana Pipeline Expansion
- New Alternatives for Noise Reduction in Gas Pipelines
- Construction Begins on Ghana's $12 Billion Petroleum Hub, But Not Without Doubts
- Missouri Loses Control Over 1.5 Million-Mile Gas Pipeline Network as Feds Step In
- Gazprom’s Grandeur Fades as Europe Moves Away from Russian Gas
- Greenpeace Ordered to Pay $667 Million to Energy Transfer Over Dakota Access Pipeline Protests
Comments