Cameron LNG Train 2 Begins Commercial Operation
HOUSTON — McDermott International, Inc. has announced the beginning of commercial operation of Train 2 at Cameron LNG, which is jointly owned by affiliates of Sempra LNG, Total, Mitsui & Co., Ltd. and Japan LNG Investment, LLC., following its substantial completion.
"Congratulations to the project team whose focus on execution excellence continues to move the Cameron LNG project forward with this significant accomplishment," said Mark Coscio, McDermott's Senior Vice President for North, Central and South America.
McDermott and its joint venture member on the project, Chiyoda, have been providing the engineering, procurement, construction and commissioning for the project since it began. The project includes three liquefaction trains with a projected export capacity of more than 12 million tonnes per annum of LNG, or approximately 1.7 billion cubic feet per day.
Cameron LNG Train 3 is on track to reach initial LNG production in the second quarter of 2020.
Related News
Related News

- 1,000-Mile Pipeline Exit Plan by Hope Gas Alarms West Virginia Producers
- Valero Plans to Shut California Refinery, Takes $1.1 Billion Hit
- Three Killed, Two Injured in Accident at LNG Construction Site in Texas
- Boardwalk’s Texas Gas Launches Open Season for 2 Bcf/d Marcellus-to-Louisiana Pipeline Expansion
- Traverse Pipeline Approved to Move 1.75 Bcf/d of Gas Along 160-Mile South Texas–Katy Route
- New Alternatives for Noise Reduction in Gas Pipelines
- Construction Begins on Ghana's $12 Billion Petroleum Hub, But Not Without Doubts
- DOE Considers Cutting Over $1.2 Billion in Carbon Capture Project Funding
- Valero Plans to Shut California Refinery, Takes $1.1 Billion Hit
- Newsom Seeks to Aid Struggling Refiners Following Valero’s California Exit
Comments