(Reuters) — U.S. energy company Dominion Energy Inc said Friday it took a $2.8 billion charge in the second quarter related to the cancellation of the Atlantic Coast natural gas pipeline from West Virginia to North Carolina.
Atlantic Coast was the most expensive U.S. gas pipeline under construction when Dominion and partner Duke Energy Corp exited the $8 billion project earlier this month due to regulatory uncertainty following years of delays and billions of dollars of cost overruns.
Atlantic Coast is just one of several U.S. oil and gas pipelines mired in legal and regulatory battles with local and environmental groups that have found numerous problems with U.S. permits issued by Trump administration agencies.
When Dominion started work on the 600-mile (966-km) pipe in the spring of 2018, the company estimated it would cost $6.0 billion to $6.5 billion and be completed in late 2019.
In the weeks before canceling the project, however, Dominion said it could finish the project in early 2022 only if it received new federal permits soon that would survive court challenges.
In addition to regulatory delays, Atlantic Coast was also hurt by a short-term hit to gas demand from the coronavirus and a longer-term hit from growing consumer interest in more clean energy projects.
Virginia is one of several states seeking to achieve 100% carbon-free power over the next two decades.
Even though gas is the cleanest fossil fuel and is considered by many energy analysts to provide a bridge from dirty coal to clean renewables, it still produces carbon.
Dominion has plans to invest up to $55 billion over the next 15 years on zero-carbon generation, energy storage, gas distribution replacement and renewable natural gas.
Dominion said it aims to achieve net-zero carbon dioxide and methane emissions from its power generation and gas infrastructure operations by 2050.
Related News
Related News
- Trump Aims to Revive 1,200-Mile Keystone XL Pipeline Despite Major Challenges
- Valero Considers All Options, Including Sale, for California Refineries Amid Regulatory Pressure
- ConocoPhillips Eyes Sale of $1 Billion Permian Assets Amid Marathon Acquisition
- ONEOK Agrees to Sell Interstate Gas Pipelines to DT Midstream for $1.2 Billion
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- U.S. LNG Export Growth Faces Uncertainty as Trump’s Tariff Proposal Looms, Analysts Say
- Tullow Oil on Track to Deliver $600 Million Free Cash Flow Over Next 2 Years
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- GOP Lawmakers Slam New York for Blocking $500 Million Pipeline Project
- Texas Oil Company Challenges $250 Million Insurance Collateral Demand for Pipeline, Offshore Operations
Comments