Enbridge U.S. TETCO NatGas Pipe Prepares to Return to Full Service
(Reuters) — Enbridge Inc's Texas Eastern Transmission (TETCO) unit said it provided all the information federal safety regulators requested and is preparing to increase pressure in its Pennsylvania to Mississippi pipeline as soon regulators approve.

TETCO declared a force majeure on May 28 after the U.S. Pipeline and Hazardous Material Safety Administration (PHMSA) required the company to reinstate a 20% pressure restriction on two of three lines (Lines 10 and 15) that make up its 30-inch system between its Kosciusko, Mississippi, and Uniontown, Pennsylvania, compressor stations effective June 1.
That reduction cut flows from Appalachia to the Gulf Coast on the 30-inch system at the Owningsville compressor station in Kentucky to an average of 1.1 billion cubic feet per day (bcfd) in June and 1.3 bcfd so far in July from an average of 1.9 bcfd in May, according to Refinitiv data.
In a notice to customers late Friday, TETCO said: "In order to expeditiously recommence operations at full operating pressure once PHMSA approval is granted, (TETCO) is proactively preparing its ... process to allow the system to operate at full operating pressure."
Previously, TETCO said it anticipated the earliest the 30-inch system could return to full pressure was late in the third quarter of 2021.
PHMSA's order came as part of the agency's increased monitoring of TETCO after three explosions in the last few years.
The first was in January 2019 in Ohio, the second in August 2019 in Kentucky, which was fatal, and the third in May 2020 in Kentucky.
Before allowing TETCO to return to full pressure after the third explosion, PHMSA required TETCO to conduct inspections and submit a request every 90 days to remain at full pressure.
PHMSA ordered the reduction after TETCO found "an anomaly" during a recent inspection that the agency wanted to investigate.
Related News
Related News

- Enbridge Plans 86-Mile Pipeline Expansion, Bringing 850 Workers to Northern B.C.
- Intensity, Rainbow Energy to Build 344-Mile Gas Pipeline Across North Dakota
- U.S. Moves to Block Enterprise Products’ Exports to China Over Security Risk
- 208-Mile Mississippi-to-Alabama Gas Pipeline Moves Into FERC Review
- Court Ruling Allows MVP’s $500 Million Southgate Pipeline Extension to Proceed
- U.S. Pipeline Expansion to Add 99 Bcf/d, Mostly for LNG Export, Report Finds
- A Systematic Approach To Ensuring Pipeline Integrity
- 275-Mile Texas-to-Oklahoma Gas Pipeline Enters Open Season
- LNG Canada Start-Up Fails to Lift Gas Prices Amid Supply Glut
- Kinder Morgan Gas Volumes Climb as Power, LNG Demand Boost Pipeline Business
Comments