U.S. Denies Dakota Access Oil Pipeline Stay Request
NEW YORK (Reuters) — A U.S. appeals court on Thursday denied a request from operators of the Dakota Access oil pipeline to freeze the company's case while it seeks a Supreme Court review in its battle to keep the line open.
The 570,000 barrel-per-day (bpd) crude oil pipeline is the largest out of the Bakken shale basin of North Dakota and operators, led by Energy Transfer LP, have been locked in a legal battle with Native American tribes on whether the line can stay open.
Early this year, a three-judge panel with the Court of Appeals for the District of Columbia Circuit ruled that the pipeline must undergo an environmental review and that the line's key permit should be thrown out. The panel, however, did not rule to shut the line. The denial of the pipeline operators' request means that the panel's previous decision is not locked in if Dakota Access operators return to the appeals court, and they could receive a different group of judges to decide on its legal case.
The Dakota Access Pipeline (DAPL) is continuing to run while its legal case plays out, but it faces the possibility of a shutdown order from a U.S. District Court. That decision is expected later this month.
Related News
Related News

- Kinder Morgan Proposes 290-Mile Gas Pipeline Expansion Spanning Three States
- Enbridge Plans 86-Mile Pipeline Expansion, Bringing 850 Workers to Northern B.C.
- Intensity, Rainbow Energy to Build 344-Mile Gas Pipeline Across North Dakota
- U.S. Moves to Block Enterprise Products’ Exports to China Over Security Risk
- Court Ruling Allows MVP’s $500 Million Southgate Pipeline Extension to Proceed
- U.S. Pipeline Expansion to Add 99 Bcf/d, Mostly for LNG Export, Report Finds
- A Systematic Approach To Ensuring Pipeline Integrity
- 275-Mile Texas-to-Oklahoma Gas Pipeline Enters Open Season
- LNG Canada Start-Up Fails to Lift Gas Prices Amid Supply Glut
- TC Energy’s North Baja Pipeline Expansion Brings Mexico Closer to LNG Exports
Comments