TC Energy Submits Restart Plan for Keystone Pipeline to US regulator
12/20/2022
(Reuters) — TC Energy Corp. has submitted a restart plan for its Keystone pipeline to U.S. safety regulator Pipeline and Hazardous Materials Safety Administration (PHMSA) which is being reviewed, according to a source on Tuesday.
The 622,000 barrels per day pipeline was shut after it spilled 14,000 barrels of oil in rural Kansas, including into a creek. Bitumen tends to sink in water, making it harder to collect than oils that float.
The rupture on Dec. 7 is the third in the last five years for the Keystone Pipeline, and the worst of the three, with cleanup expected to take weeks or months.
The response team has so far recovered 7,233 barrels of oil from Mill Creek.
TC Energy was not immediately available for a comment.
Related News
Related News
Sign up to Receive Our Newsletter

- 416-Mile Coastal GasLink Pipeline Project 98% Complete
- FERC Approves TC Energy's 1,377-Mile West Coast Pipeline Expansion
- Kinder Morgan to Buy NextEra’s 462-Mile Texas Pipeline System for $1.8 Billion
- Williams' Gas Pipeline in Idaho Ruptures, Company Challenges Explosion Allegations
- Biden Awards $7 Billion in Hydrogen Hub Money to 16 States
- 416-Mile Coastal GasLink Pipeline Project 98% Complete
- UAE's ADNOC Awards $17 Billion of Contracts for Gas Project, Including Subsea Pipelines
- HVO: Fuel for the Future
- Analysis: Canada May Struggle to Recoup $26 Billion Cost of Trans Mountain Pipeline
- Biden Awards $7 Billion in Hydrogen Hub Money to 16 States
Pipeline Project Spotlight
Owner:
East African Crude Oil Pipeline Company
Project:
East African Crude Oil Pipeline (EACOP)
Type:
TotalEnergies in discussions with a Chinese company after Russian supplier Chelpipe was hit by sanctions.
Length:
902 miles (1,443 km)
Capacity:
200,000 b/d
Start:
2022
Completion:
2025
Comments