QUITO (Reuters) — OCP Ecuador, operator of the South American country's private oil pipeline, said that repairs to tubing damaged last weekend by falling rocks will take between seven and 10 days because of new damage sustained in the same area.
A rock fall following rains in the Piedra Fina zone of Ecuador's Amazon caused part of the OCP heavy crude pipeline to split late on Friday, causing an oil spill.
Ecuador's environment ministry said on Monday that OCP will face legal consequences for the spill, which occurred within a protected area of the country's rainforest.
The new damage occurred on Monday near the rupture reported over the weekend, OCP said in a Tuesday statement.
"There are effects that require an intervention to achieve a safe operation," the company said. "Technical personnel from the transport company estimate the repair of the pipeline will take between seven and 10 days from this date."
Regressive erosion advancing along the Coca river has caused problems for both the privately operated OCP pipeline and the state-owned SOTE pipeline since 2020. As a result, in December both pipelines suspended pumping, leading the government to declare force majeure on the majority of the country's oil exports and production contracts.
Related News
Related News

- Missouri Loses Control Over 1.5 Million-Mile Gas Pipeline Network as Feds Step In
- 1,000-Mile Pipeline Exit Plan by Hope Gas Alarms West Virginia Producers
- Valero Plans to Shut California Refinery, Takes $1.1 Billion Hit
- Greenpeace Ordered to Pay $667 Million to Energy Transfer Over Dakota Access Pipeline Protests
- Canada’s Canceled Oil Pipelines: The Projects That Didn’t Make It
- New Alternatives for Noise Reduction in Gas Pipelines
- Editor’s Notebook: Fire Fuels Pipeline Concerns
- Missouri Loses Control Over 1.5 Million-Mile Gas Pipeline Network as Feds Step In
- Enbridge Plans $2 Billion Upgrade for North America’s Largest Crude Pipeline
- South Dakota Governor Signs Bill Banning Eminent Domain for Carbon Pipeline
Comments