NextEra Takes $800 Million Charge for Mountain Valley Pipeline
(Reuters) — NextEra Energy said one of its units recorded an $800 million impairment charge in the first quarter as the U.S. renewable energy company re-evaluates its investment in the long-delayed Mountain Valley natural gas pipeline from West Virginia to Virginia.
NextEra said in a U.S. Securities and Exchange Commission filing that its NextEra Energy Resources unit and other Mountain Valley joint venture partners continue to evaluate options and next steps for the project.
The U.S. Court of Appeals for the Fourth Circuit over the last month has invalidated key permits for the project issued by the U.S. Fish and Wildlife Service and the U.S. Forest Service.
The court rulings were the latest setback for the pipeline, which is years behind schedule and billions of dollars over budget.
Several analysts have said the court decisions would likely delay the project startup until 2023 or 2024.
Before the latest setbacks, Equitrans Midstream, the project's lead partner, said it expected the pipeline to cost about $6.2 billion and enter service in the summer of 2022.
Equitrans said in January it was "evaluating the project’s next steps and timing considerations," noting total work on the pipeline was "nearly 94% complete."
Mountain Valley is one of several U.S. pipeline projects delayed by regulatory and legal fights with environmental and local groups which found problems with federal permits issued during President Donald Trump's administration.
When Mountain Valley construction started in February 2018, Equitrans estimated the 303-mile (488-km), 2 Bcf/d project would cost about $3.5 billion and enter service by late 2018.
Equitrans has a 47.8% ownership interest in Mountain Valley and will operate the pipeline.
The Mountain Valley venture is owned by units of Equitrans, NextEra, Consolidated Edison, AltaGas and RGC Resources.
Related News
Related News

- Enbridge Plans 86-Mile Pipeline Expansion, Bringing 850 Workers to Northern B.C.
- Intensity, Rainbow Energy to Build 344-Mile Gas Pipeline Across North Dakota
- U.S. Moves to Block Enterprise Products’ Exports to China Over Security Risk
- Strike Pioneers First-of-Its-Kind Pipe-in-Pipe Installation on Gulf Coast with Enbridge
- 208-Mile Mississippi-to-Alabama Gas Pipeline Moves Into FERC Review
- U.S. Pipeline Expansion to Add 99 Bcf/d, Mostly for LNG Export, Report Finds
- A Systematic Approach To Ensuring Pipeline Integrity
- 275-Mile Texas-to-Oklahoma Gas Pipeline Enters Open Season
- LNG Canada Start-Up Fails to Lift Gas Prices Amid Supply Glut
- Strike Pioneers First-of-Its-Kind Pipe-in-Pipe Installation on Gulf Coast with Enbridge
Comments