Regas Ship Arrives for Hong Kong's First LNG Import Terminal
(Reuters) — The world's largest floating storage and regasification unit (FSRU) has arrived in Hong Kong to serve the city's first LNG import terminal, said CLP Power Hong Kong Ltd and Hong Kong Electric Co. Ltd.
The FSRU arrived on April 13 and will set sail after checks and port clearance procedures to the offshore Hong Kong LNG terminal next week for final commissioning of the project, the two companies said in a joint statement on Thursday evening.
The 4 million tonnes a year import terminal project has been delayed by more than two years as the COVID-19 pandemic slowed construction.
To be renamed the Bauhinia Spirit, the FSRU owned by Mitsui O.S.K. Lines 9104.T and Vopak, is 345 meters long and has storage capacity of 263,000 cubic meters.
The vessel will be moored at the jetty of Hong Kong LNG terminal to receive, store and regassify LNG.
The LNG terminal, jointly developed by CLP Power and HK Electric, is scheduled to start operating in mid-2023. CLP Power last month issued a tender to purchase a commissioning cargo for the terminal for delivery in May.
Related News
Related News

- Kinder Morgan Proposes 290-Mile Gas Pipeline Expansion Spanning Three States
- Valero Plans to Shut California Refinery, Takes $1.1 Billion Hit
- Three Killed, Two Injured in Accident at LNG Construction Site in Texas
- Tallgrass to Build New Permian-to-Rockies Pipeline, Targets 2028 Startup with 2.4 Bcf Capacity
- TC Energy Approves $900 Million Northwoods Pipeline Expansion for U.S. Midwest
- U.S. Pipeline Expansion to Add 99 Bcf/d, Mostly for LNG Export, Report Finds
- Enbridge Adds Turboexpanders at Pipeline Sites to Power Data Centers in Canada, Pennsylvania
- Great Basin Gas Expansion Draws Strong Shipper Demand in Northern Nevada
- Cheniere Seeks FERC Approval to Expand Sabine Pass LNG Facility
- Heath Consultants Exits Locate Business to Expand Methane Leak Detection Portfolio