Gas Starts Flowing to Freeport LNG Export Plant in Texas
(Reuters) - Freeport LNG's long-shut LNG export plant in Texas started receiving pipeline natural gas over the long U.S. Martin Luther King Jr holiday weekend, according to Refinitiv data.
U.S. LNG exports have been steadily increasing for years and Freeport, the second biggest U.S. LNG export plant, is one of a number of key facilities for shipments around the world, where demand has soared following Russia's decision to largely cut off piped gas supply to Europe after Moscow's invasion of Ukraine.
Gas started flowing to Freeport on Jan. 14 and was on track to reach 69 MMcf/d on Tuesday, according to data from Refinitiv.
A source familiar with the flows said they were within the plant's pre-treatment facility and were maintaining the flare system.
The last time gas flowed to Freeport was in late December, also to maintain a flare system.
Officials at Freeport, which shut in a fire on June 8, 2022, said on Tuesday the plant was still on track to restart in the second half of January, pending regulatory approvals.
Freeport has not yet filed a request with federal regulators to restart the plant, according to a source familiar with the company's filings.
Gas futures rose about 8% on Tuesday from an 18-month low in the prior session on the possibility Freeport could restart soon and on forecasts for much colder weather and higher heating demand over the next two weeks than previously expected.
Freeport's restart timeline, however, has been delayed many times from October to November to December and then most recently to January.
Even when the company was saying the plant could restart last year, many analysts said it was likely to take Freeport until the first or second quarter of 2023 to get the plant ready due to the large amount of work needed to satisfy federal regulators, including training staff in new safety procedures.
Last week after sources told Reuters the plant would not return until February or later, at least two LNG vessels gave up on Freeport and moved to other ports, according to ship tracking data from Refinitiv.
Whenever Freeport returns, U.S. gas demand will jump. The plant can turn about 2.1 Bcf/d of gas into LNG, which is about 2% of U.S. daily production.
Related News
Related News
- Phillips 66 to Shut LA Oil Refinery, Ending Major Gasoline Output Amid Supply Concerns
- FERC Sides with Williams in Texas-Louisiana Pipeline Dispute with Energy Transfer
- U.S. Appeals Court Blocks Kinder Morgan’s Tennessee Pipeline Permits
- ConocoPhillips Eyes Sale of $1 Billion Permian Assets Amid Marathon Acquisition
- Valero Considers All Options, Including Sale, for California Refineries Amid Regulatory Pressure
- U.S. Appeals Court Blocks Kinder Morgan’s Tennessee Pipeline Permits
- Malaysia’s Oil Exports to China Surge Amid Broader Import Decline
- U.S. LNG Export Growth Faces Uncertainty as Trump’s Tariff Proposal Looms, Analysts Say
- Marathon Oil to Lay Off Over 500 Texas Workers Ahead of ConocoPhillips Merger
- Valero Considers All Options, Including Sale, for California Refineries Amid Regulatory Pressure
Comments