Energy Transfer to Continue Lake Charles LNG Project Despite DOE Rehearing Denial
(Reuters) — Pipeline operator and LNG developer Energy Transfer on Friday said it will continue construction of its Lake Charles LNG project despite a rehearing denial by the U.S. Department of Energy.
RELATED: DOE Refuses Pipeline Operator Energy Transfer's Rehearing Request for LNG Project
The DOE on Wednesday rejected Energy Transfer's request for a second extension of its multibillion-dollar LNG export project. It would consider another application if Energy Transfer is unable to meet its 2025 deadline, the DOE said.
"In light of the significant progress of Lake Charles LNG, we plan to continue to develop the project which may include the use of Lake Charles’ existing DOE export authorization," an Energy Transfer spokesperson told Reuters.
Related News
Related News

- 1,000-Mile Pipeline Exit Plan by Hope Gas Alarms West Virginia Producers
- Valero Plans to Shut California Refinery, Takes $1.1 Billion Hit
- Three Killed, Two Injured in Accident at LNG Construction Site in Texas
- Greenpeace Ordered to Pay $667 Million to Energy Transfer Over Dakota Access Pipeline Protests
- Boardwalk’s Texas Gas Launches Open Season for 2 Bcf/d Marcellus-to-Louisiana Pipeline Expansion
- New Alternatives for Noise Reduction in Gas Pipelines
- Construction Begins on Ghana's $12 Billion Petroleum Hub, But Not Without Doubts
- Missouri Loses Control Over 1.5 Million-Mile Gas Pipeline Network as Feds Step In
- Gazprom’s Grandeur Fades as Europe Moves Away from Russian Gas
- Greenpeace Ordered to Pay $667 Million to Energy Transfer Over Dakota Access Pipeline Protests
Comments