US Mountain Valley Gas Pipeline Moving Forward, Capacity May Be Limited
(Reuters) — The $6.6 billion Mountain Valley natural gas pipeline from West Virginia to Virginia is on track to get final permits by Saturday, moving the long-delayed project closer to re-starting construction.
Some analysts, however, said that even when the pipe enters service, which could be as soon as the end of 2023, it would only operate at half capacity or less due to transmission constraints.
Equitrans Midstream Corp., the lead partner building Mountain Valley, disputed that half-capacity analysis and noted that it is normal for gas markets to take time to fully adjust to new large-scale projects.
Mountain Valley "is not being built for the short term. (It) will meet increasing gas demand and improve reliability and affordability for domestic consumers for decades to come," Equitrans spokesperson Natalie Cox told Reuters in an email.
Mountain Valley has said it expects to resume construction after the U.S. Army Corps of Engineers issues a water permit. That should happen by Saturday as mandated by the Fiscal Responsibility Act, which ended the debt ceiling crisis.
"We will request the administrative authorizations necessary to resume full construction in the near future," Cox said, noting that Mountain Valley continues to target project completion by year-end 2023.
Mountain Valley is one of several U.S. projects delayed by regulatory and legal fights with environmental and local groups in recent years. The pipe is key to unlocking more gas supplies in Appalachia, the nation's biggest shale gas basin.
But analysts at energy consulting firm East Daley Analytics said Mountain Valley will only run at about 35% of its 2 billion cubic feet per day (Bcf/d) capacity when it is finally built.
That's because the Transcontinental Gas Pipe Line (Transco) system into which Mountain Valley will connect in Virginia has limited takeaway capacity, East Daley said.
Transco is owned by U.S. energy company Williams Cos Inc. Officials at Williams were not immediately available for comment.
Environmental groups, meanwhile, continue to challenge Mountain Valley's permits in court.
"There is no reason to think they could build and operate this project safely, and now analysts are saying that if (Mountain Valley) is completed, it would only run at less than half capacity," said Caroline Hansley, senior campaign representative at the Sierra Club, an environmental group opposed to the pipeline.
When Mountain Valley started construction in February 2018, Equitrans estimated the 303-mile (488-km) project would cost about $3.5 billion and enter service by late 2018.
Mountain Valley is owned by units of Equitrans, NextEra Energy Inc., Consolidated Edison Inc., AltaGas Ltd. and RGC Resources Inc.
Related News
Related News
- Trump Aims to Revive 1,200-Mile Keystone XL Pipeline Despite Major Challenges
- Valero Considers All Options, Including Sale, for California Refineries Amid Regulatory Pressure
- ConocoPhillips Eyes Sale of $1 Billion Permian Assets Amid Marathon Acquisition
- ONEOK Agrees to Sell Interstate Gas Pipelines to DT Midstream for $1.2 Billion
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- U.S. LNG Export Growth Faces Uncertainty as Trump’s Tariff Proposal Looms, Analysts Say
- Tullow Oil on Track to Deliver $600 Million Free Cash Flow Over Next 2 Years
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- GOP Lawmakers Slam New York for Blocking $500 Million Pipeline Project
- Texas Oil Company Challenges $250 Million Insurance Collateral Demand for Pipeline, Offshore Operations
Comments