Trans Mountain to Finish Final Segment of Oil Pipeline Expansion in April
(Reuters) — Trans Mountain will finish building the final segment of its Canadian oil pipeline expansion in April, according to a construction schedule the corporation filed on Monday with a regulator.
The Canadian government-owned C$34-billion ($25.07 billion) pipeline expansion will nearly triple the flow of crude from Alberta to Canada's Pacific Coast to 890,000 barrels per day, but has been plagued by years of delays, construction problems and cost overruns.
RELATED: Trans Mountain Pipeline Expansion Nears 95% Completion, Set to Triple Crude Oil Capacity
Spread 5-B is the last segment to complete and Trans Mountain's schedule filed to the Canada Energy Regulator shows construction and testing wrapping up this month.
Trans Mountain said last month it has started filling its expanded pipeline in a staged process, but still faced technical challenges.
The pipeline, scheduled to be in service in the second quarter, is expected to raise Canadian crude prices just as producers boost production.
($1 = 1.3562 Canadian dollars)
Related News
Related News
- Trump Aims to Revive 1,200-Mile Keystone XL Pipeline Despite Major Challenges
- Valero Considers All Options, Including Sale, for California Refineries Amid Regulatory Pressure
- ConocoPhillips Eyes Sale of $1 Billion Permian Assets Amid Marathon Acquisition
- ONEOK Agrees to Sell Interstate Gas Pipelines to DT Midstream for $1.2 Billion
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- U.S. LNG Export Growth Faces Uncertainty as Trump’s Tariff Proposal Looms, Analysts Say
- Tullow Oil on Track to Deliver $600 Million Free Cash Flow Over Next 2 Years
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- GOP Lawmakers Slam New York for Blocking $500 Million Pipeline Project
- Texas Oil Company Challenges $250 Million Insurance Collateral Demand for Pipeline, Offshore Operations
Comments