Williams Says Court Rules in Its Favor in Pipeline Dispute with Energy Transfer
(Reuters) — Pipeline operator Williams said on Wednesday a Louisiana court has ruled in its favor in a dispute with its rival Energy Transfer over a pipeline construction.
The two firms were locked in a tussle over Williams' Louisiana Energy Gateway (LEG) Project, under construction in Texas and Louisiana, after Energy Transfer pushed back on the line for crossing its own systems.
RELATED: Energy Transfer Faces Allegations of Anti-Competitive Practices in Louisiana Pipeline Dispute
The ruling by Louisiana's 36th Judicial District Court of Beauregard Parish was in company's favor on all seven crossings, and enjoined Energy Transfer from interfering with the construction, operation and maintenance of the pipeline, a Williams spokesperson said in a statement.
The 1.8-billion-cubic-feet-per-day system was supposed to be operational this year but has been delayed until the second half of 2025 following the dispute.
RELATED: Williams Foresees Victory in Energy Transfer Dispute Over Louisiana Gas Pipeline
Energy Transfer did not immediately respond to a Reuters request for comment.
The line would feed gas from the Haynesville shale field to the U.S. Gulf Coast.
Related News
Related News

- Kinder Morgan Proposes 290-Mile Gas Pipeline Expansion Spanning Three States
- Enbridge Plans 86-Mile Pipeline Expansion, Bringing 850 Workers to Northern B.C.
- Intensity, Rainbow Energy to Build 344-Mile Gas Pipeline Across North Dakota
- Tallgrass to Build New Permian-to-Rockies Pipeline, Targets 2028 Startup with 2.4 Bcf Capacity
- U.S. Moves to Block Enterprise Products’ Exports to China Over Security Risk
- U.S. Pipeline Expansion to Add 99 Bcf/d, Mostly for LNG Export, Report Finds
- A Systematic Approach To Ensuring Pipeline Integrity
- 275-Mile Texas-to-Oklahoma Gas Pipeline Enters Open Season
- TC Energy’s North Baja Pipeline Expansion Brings Mexico Closer to LNG Exports
- US Poised to Become Net Exporter of Crude Oil in 2023
Comments