(Reuters) — TotalEnergies was preparing on Friday to restart the gasoline-producing fluidic catalytic cracker (FCC) over the weekend at its 238,000 barrel-per-day (bpd) Port Arthur, Texas refinery, said people familiar with plant operations.
Following the FCC’s restart, the company plans to restart the refinery’s coker and small crude distillation unit (CDU), the sources said on Friday.
The 76,000-bpd FCC was shut by a leak and a clamp had to be fabricated, the sources said. The clamp was installed on Thursday.
The 60,000-bpd coker and 40,000-bpd ACU-2 CDU were shut after the FCC was idled, according to the sources. Once the coker restarts, ACU-2 will be brought back up into production.
The TotalEnergies refinery has struggled since late November after the end of a three-month overhaul on the FCC.
It struggled to resume full production until being hit by a plantwide power outage on Jan. 16. The refinery returned to normal production by Feb. 21 following the outage.
TotalEnergies reported that two sulfur recovery units malfunctioned on March 7, according to a notice to the Texas Commission on Environmental Quality.
ACU-2 is the smaller of two CDUs that begin the refining process by breaking down crude oil into feedstocks for all other units at the refinery.
The FCC uses a fine powder catalyst to convert gas oil under high heat and pressure into gasoline.
The coker converts residual crude oil from distillation units into either feedstocks to make motor fuels or petroleum coke, which can be a substitute for coal.
Related News
Related News

- Enbridge Plans 86-Mile Pipeline Expansion, Bringing 850 Workers to Northern B.C.
- Intensity, Rainbow Energy to Build 344-Mile Gas Pipeline Across North Dakota
- U.S. Moves to Block Enterprise Products’ Exports to China Over Security Risk
- 208-Mile Mississippi-to-Alabama Gas Pipeline Moves Into FERC Review
- Court Ruling Allows MVP’s $500 Million Southgate Pipeline Extension to Proceed
- U.S. Pipeline Expansion to Add 99 Bcf/d, Mostly for LNG Export, Report Finds
- A Systematic Approach To Ensuring Pipeline Integrity
- 275-Mile Texas-to-Oklahoma Gas Pipeline Enters Open Season
- LNG Canada Start-Up Fails to Lift Gas Prices Amid Supply Glut
- Kinder Morgan Gas Volumes Climb as Power, LNG Demand Boost Pipeline Business
Comments