BP Delays Whiting Refinery Restart, Fuel Prices Rise in Chicago Market
(Reuters) — BP has delayed the restart of a crude distillation unit and a coker at its 435,000 barrel-per-day Whiting, Indiana, refinery from maintenance, boosting fuel prices in the Chicago market, industry sources said on Tuesday.
BP, which started the planned turnaround at the largest refinery in the U.S. Midwest in late September, began restarting units involved in the turnaround in early November. The restart had been scheduled for mid-November.
A source said at least two of the units -the 250,000-bbl/d sour crude distillation unit and the 102,000-bbl/d coker unit - experienced issues during the restart process. The units are expected to be back online this week, the source added.
Traders told Reuters that they had to find other sources of gasoline and diesel in the past few days.
Chicago-market CBOB gasoline CBOB-DIFF-MC traded half a cent per gallon below futures benchmark on the New York Mercantile Exchange RBc1 on Tuesday, traders said, compared with a 14-cent discount in the previous session.
Chicago ultra-low sulfur diesel ULSD-DIFF-MC traded at a four-cent discount to futures HOc1, compared with a 15-cent discount previously.
BP did not immediately respond to inquiries about the units experiencing issues during startup.
It issued an alert on Monday about flaring at the Whiting refinery. "Flares are an essential safety device that helps the refinery safely manage excess gases during periods of maintenance or operational disruptions," the company said in a statement.
The flaring concluded on Monday, a BP spokesperson said.
In February, BP shut the refinery for roughly a month due to a plantwide power outage.
Related News
Related News

- Enbridge Plans 86-Mile Pipeline Expansion, Bringing 850 Workers to Northern B.C.
- Intensity, Rainbow Energy to Build 344-Mile Gas Pipeline Across North Dakota
- Energy Transfer to Build $5.3 Billion Permian Gas Pipeline to Supply Southwest
- Enbridge Sees High Demand to Expand 593-Mile Canada-to-U.S. Gulf Oil Pipeline
- Strike Pioneers First-of-Its-Kind Pipe-in-Pipe Installation on Gulf Coast with Enbridge
- A Systematic Approach To Ensuring Pipeline Integrity
- 275-Mile Texas-to-Oklahoma Gas Pipeline Enters Open Season
- LNG Canada Start-Up Fails to Lift Gas Prices Amid Supply Glut
- Strike Pioneers First-of-Its-Kind Pipe-in-Pipe Installation on Gulf Coast with Enbridge
- Enbridge Sees High Demand to Expand 593-Mile Canada-to-U.S. Gulf Oil Pipeline
Comments