Exxon Mobil, Qatar Receive 3-Year Extension for Golden Pass LNG Plant in Texas
(Reuters) - Federal regulators on Thursday gave an Exxon Mobil and Qatar Energy LNG joint venture a 3-year extension to finish building their Golden Pass LNG plant, a regulatory document showed.
The extension was granted due to delays caused when lead construction contractor Zachry Holdings filed for bankruptcy in March, according to a Federal Energy Regulatory Commission filing.
The project, at the Sabine Pass site of a former gas-import terminal that was converted to process natural gas for LNG exports, is one of two large U.S. LNG facilities whose startups were expected to significantly expand supplies from the world's top exporter of the superchilled fuel in the next 12 months.
The project's original main contractor, Zachry Holdings filed for Chapter 11 bankruptcy protection, saying the Golden Pass project — known as GPX — was at least $2.4 billion over the original budget.
Golden Pass has yet to announce a new EPC contractor and has been in negotiations with McDermott International MCDIF.PK to be the lead contractor on the project.
Related News
Related News

- Trump Puts Keystone XL Pipeline Back in Discussion, Though Revival Faces Developer Resistance
- Army Corps Lists Enbridge’s Line 5 as ‘Emergency’ Project Eligible to Bypass Environmental Review
- Missouri Loses Control Over 1.5 Million-Mile Gas Pipeline Network as Feds Step In
- Energy Transfer Wins New York Court Ruling in $150 Million Pipeline Fraud Case
- $3 Billion Natural Gas Pipeline Expansion to Add 1.3 Bcf Capacity in Southeast Region
- Kinder Morgan Approves $1.4 Billion Mississippi Crossing Project to Boost Southeast Gas Supply
- Army Corps Lists Enbridge’s Line 5 as ‘Emergency’ Project Eligible to Bypass Environmental Review
- India’s GAIL Eyes U.S. LNG Deals Following Trump’s Policy Shift
- TC Energy Beats Q4 Profit Estimates, Driven by Mexico Pipelines' Success
- Michigan Court Backs Permits for Enbridge’s Line 5 Pipeline Tunnel Project
Comments