FERC Sides with Williams in Texas-Louisiana Pipeline Dispute with Energy Transfer
By Mary Holcomb, Digital Editor
(P&GJ) — The Federal Energy Regulatory Commission (FERC) has rejected Energy Transfer LP's request to challenge the jurisdictional status of a major pipeline project by The Williams Companies Inc. (Williams), according to a Sept. 27 ruling.
In its petition, Energy Transfer sought an order requiring Williams to demonstrate why its Louisiana Energy Gateway (LEG) pipeline system in Texas and Louisiana should not fall under FERC's jurisdiction. The petition centered on whether portions of the pipeline are "gathering" facilities or subject to federal oversight as transmission lines.
Williams plans to build the LEG System, a massive project designed to gather and process natural gas from the Haynesville Shale region. The system will consist of two major segments: the Haynesville Spine, a 64-mile pipeline system in Louisiana, and the Juniper South segment, a 110-mile pipeline. Energy Transfer argued that the size and scope of the system make it more like a transmission network, which would place it under FERC’s regulation.
However, FERC disagreed. The commission ruled that the LEG System will function as a gathering facility, exempt from its jurisdiction under the Natural Gas Act (NGA). FERC applied its "primary function test," considering the system's geographic configuration, pipeline size, and operational purpose, concluding that it meets the criteria for non-jurisdictional gathering activities.
In dismissing Energy Transfer’s petition, FERC stated that Williams' LEG System serves an essential role in gathering and processing gas from productive regions like the Haynesville Shale, Austin Chalk, and Tuscaloosa Marine Shale. The commission found no basis to treat the LEG System as part of Williams' larger interstate Transco pipeline system, as argued by Energy Transfer.
This decision clears the path for Williams to proceed with the construction and operation of the LEG pipeline as planned, exempt from federal oversight under the NGA.
Related News
Related News
- Williams Seeks Emergency Certificate to Operate $1 Billion Mid-Atlantic Gas Pipeline After Court Reversal
- Energy Transfer Subsidiary Selects KTJV for Lake Charles LNG Export Project
- FERC Sides with Williams in Texas-Louisiana Pipeline Dispute with Energy Transfer
- Phillips 66 to Shut LA Oil Refinery, Ending Major Gasoline Output Amid Supply Concerns
- U.S. Appeals Court Blocks Kinder Morgan’s Tennessee Pipeline Permits
- Malaysia’s Oil Exports to China Surge Amid Broader Import Decline
- U.S. LNG Export Growth Faces Uncertainty as Trump’s Tariff Proposal Looms, Analysts Say
- Marathon Oil to Lay Off Over 500 Texas Workers Ahead of ConocoPhillips Merger
- Another Major U.S. Oil Refinery Shutting Down as Lyondell Confirms Houston Closure
- Four Petroleum Liquids Pipelines Completed in U.S. Since 2023
Comments