Glenfarne’s Alaska LNG Project Attracts $115 Billion in Partner Bids
(Reuters) — Glenfarne said on June 3 that its unit, Glenfarne Alaska LNG, has completed the first round of its strategic partner selection process with over 50 companies who have formally expressed interest for over $115 billion of contract value for the Alaska LNG project.
The 807-mile 42-inch pipeline project is capable of transporting natural gas to meet both Alaska's domestic needs and supply the full 20 million tonnes per annum (mtpa) Alaska LNG export facility, the company said.
Phase One is expected to deliver natural gas about 765 miles from the North Slope to the Anchorage region.
Additionally, the Phase Two will add nearly 42 miles of pipeline under the Cook Inlet to the Alaska LNG export facility in Nikiski, which will be constructed simultaneously with the LNG export facility.
Glenfarne expects a final investment decision on the domestic portion of the Alaska LNG pipeline by the end of the fourth quarter this year.
Related News
Related News

- Kinder Morgan Proposes 290-Mile Gas Pipeline Expansion Spanning Three States
- Three Killed, Two Injured in Accident at LNG Construction Site in Texas
- Tallgrass to Build New Permian-to-Rockies Pipeline, Targets 2028 Startup with 2.4 Bcf Capacity
- TC Energy Approves $900 Million Northwoods Pipeline Expansion for U.S. Midwest
- U.S. Moves to Block Enterprise Products’ Exports to China Over Security Risk
- U.S. Pipeline Expansion to Add 99 Bcf/d, Mostly for LNG Export, Report Finds
- Enbridge Adds Turboexpanders at Pipeline Sites to Power Data Centers in Canada, Pennsylvania
- Great Basin Gas Expansion Draws Strong Shipper Demand in Northern Nevada
- Cheniere Seeks FERC Approval to Expand Sabine Pass LNG Facility
- Heath Consultants Exits Locate Business to Expand Methane Leak Detection Portfolio
Comments