Lithuania LNG Terminal Plan Delayed

Lithuanian state-controlled energy terminal operator Klaipedos Nafta delayed approval of a contractor to build a link to connect its planned LNG terminal to the distribution grid pending a probe of the tender terms. This could hold back launch of the gas platform in late 2014.

The disputed tender is to build a 20-km pipeline linking the floating LNG terminal to Lithuania’s gas distribution network by Oct. 1, 2014. The 2-3 Bcm/y regasification and storage facility is planned to go into operation by the end of next year.

The plan would end Lithuania’s 100% reliance on imported Russian gas, hinges on unbundling national gas company Lietuvos dujos, which controls sales and the distribution network. The new Lithuanian government has exhibited a far less confrontational approach to Moscow, and said earlier this month that it plans to talk to Russia about the plan, although it maintains that it will carry it out.

Related Articles

Comments

{{ error }}
{{ comment.comment.Name }} • {{ comment.timeAgo }}
{{ comment.comment.Text }}