North Dakota Regulators Eye Fine Against Pipeline Company

BISMARCK, N.D. (AP) — North Dakota regulators are proposing a fine of at least $15,000 against the company building the four-state Dakota Access pipeline.
The Public Service Commission said Monday in a complaint that a subsidiary of Texas-based Energy Transfer Partners didn’t get regulators’ approval to proceed with construction after artifacts, including stone cairns, were found last month.
The company diverted construction so the artifacts weren’t disturbed, a plan the State Historic Preservation Office concurred with. But the PSC says the company should have gotten clearance from regulators.
Energy Transfer Partners can agree to a fine or request a hearing. Spokeswoman Vicki Granado says the company doesn’t think it did anything wrong but is working with the PSC.
The $3.8 billion pipeline will carry North Dakota oil through South Dakota and Iowa to Illinois.
Related News
Related News

- Kinder Morgan Proposes 290-Mile Gas Pipeline Expansion Spanning Three States
- Enbridge Plans 86-Mile Pipeline Expansion, Bringing 850 Workers to Northern B.C.
- Three Killed, Two Injured in Accident at LNG Construction Site in Texas
- Tallgrass to Build New Permian-to-Rockies Pipeline, Targets 2028 Startup with 2.4 Bcf Capacity
- TC Energy Approves $900 Million Northwoods Pipeline Expansion for U.S. Midwest
- U.S. Pipeline Expansion to Add 99 Bcf/d, Mostly for LNG Export, Report Finds
- Enbridge Adds Turboexpanders at Pipeline Sites to Power Data Centers in Canada, Pennsylvania
- Great Basin Gas Expansion Draws Strong Shipper Demand in Northern Nevada
- Cheniere Seeks FERC Approval to Expand Sabine Pass LNG Facility
- Heath Consultants Exits Locate Business to Expand Methane Leak Detection Portfolio
Comments