North Dakota Regulators Challenge Pipeline Developer Argument

BISMARCK, N.D. (AP) — Staffers with the North Dakota Public Service Commission say there’s no doubt the developer of the four-state, $3.8 billion Dakota Access oil pipeline violated rules regarding reporting Native American artifacts.
In October, the company diverted construction around Native American artifacts without running the plan by the commission, which oversees pipelines.
ETP has said that it shouldn’t be fined because state law says there needs to be a willful violation.
Schuh said in his Dec. 15 response that a fine should be imposed regardless of intent.
The PSC will decide whether to dismiss the case or schedule a hearing.
Via attorney John Schuh, the PSC staffers urge the commission to move forward with a fine of at least $15,000 for Dallas-based Energy Transfer Partners.
Related News
Related News

- Kinder Morgan Proposes 290-Mile Gas Pipeline Expansion Spanning Three States
- Enbridge Plans 86-Mile Pipeline Expansion, Bringing 850 Workers to Northern B.C.
- Intensity, Rainbow Energy to Build 344-Mile Gas Pipeline Across North Dakota
- Tallgrass to Build New Permian-to-Rockies Pipeline, Targets 2028 Startup with 2.4 Bcf Capacity
- TC Energy Approves $900 Million Northwoods Pipeline Expansion for U.S. Midwest
- A Systematic Approach To Ensuring Pipeline Integrity
- U.S. Pipeline Expansion to Add 99 Bcf/d, Mostly for LNG Export, Report Finds
- Enbridge Adds Turboexpanders at Pipeline Sites to Power Data Centers in Canada, Pennsylvania
- Great Basin Gas Expansion Draws Strong Shipper Demand in Northern Nevada
- Cheniere Seeks FERC Approval to Expand Sabine Pass LNG Facility
Comments