NEXUS Pipeline Construction Gets Green Light
10/11/2017
FERC has approved Enbridge’s request to begin construction of the NEXUS Gas Transmission Project, except for the following locations:
- North Country National Scenic Trail at milepost 3.5 and Iron Horse Trail at milepost 17.0
- From milepost 130.5 to milepost 133.0 and milepost 151.5 to milepost 162.0
In addition, according to FERC’s Alisa M. Lykens, before beginning HDD operations, the company must complete the following directives:
- Filing supplemental information to comply with Environmental Condition 38, affirming it will utilize a down-hole annular pressure tool during the entire pilot hole drilling process and while reaming beneath sensitive environmental features (such as wetlands and waterbodies), or provide suitable alternative methods for monitoring the borehole annular pressure during reaming
- Consulting with the appropriate state agencies to determine the location of inactive, abandoned, and orphaned oil and gas wells within 500 feet of the HDD alignment at that site and filing a statement with the Secretary of the Commission affirming there are no inactive, abandoned, or orphaned oil and gas wells within 500 feet of the HDD. If wells are present, Enbridge must file a site-specific plan to prevent the communication/cross-contamination of drilling fluids with the wells during HDD for review and written approval by the Director of the Office of Energy Projects (OEP).
- At sites where the drill path passes through unconsolidated material based on previous geotechnical borings, including at the Tuscarawas River, a quantified hydrofracture and inadvertent return risk assessment must be filed with the Secretary of the Commission, for review and written approval of the Director of OEP, for those HDDs where the alignment is within unconsolidated material using empirical methods such as the “Delft Method” in conjunction with lithologic information from previous borings at the site, or additional borings must be conducted at the site to define the depth to bedrock and re-design the drill path to remain in bedrock over the entire length of the drill.
Related News
Related News
Sign up to Receive Our Newsletter
- Trump Aims to Revive 1,200-Mile Keystone XL Pipeline Despite Major Challenges
- Valero Considers All Options, Including Sale, for California Refineries Amid Regulatory Pressure
- ConocoPhillips Eyes Sale of $1 Billion Permian Assets Amid Marathon Acquisition
- ONEOK Agrees to Sell Interstate Gas Pipelines to DT Midstream for $1.2 Billion
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- U.S. LNG Export Growth Faces Uncertainty as Trump’s Tariff Proposal Looms, Analysts Say
- Tullow Oil on Track to Deliver $600 Million Free Cash Flow Over Next 2 Years
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- GOP Lawmakers Slam New York for Blocking $500 Million Pipeline Project
- Texas Oil Company Challenges $250 Million Insurance Collateral Demand for Pipeline, Offshore Operations
Pipeline Project Spotlight
Owner:
East African Crude Oil Pipeline Company
Project:
East African Crude Oil Pipeline (EACOP)
Type:
TotalEnergies in discussions with a Chinese company after Russian supplier Chelpipe was hit by sanctions.
Length:
902 miles (1,443 km)
Capacity:
200,000 b/d
Start:
2022
Completion:
2025