FERC Issues Draft EIS for Midship Project
The Federal Energy Regulatory Commission (FERC) today issued a draft environmental impact statement (EIS) for the Midship Project, which includes the construction of the following facilities in Oklahoma:
- 199.6 miles of new 36-inch-diameter natural gas pipeline in Kingfisher, Canadian, Grady, Garvin, Stephens, Carter, Johnston, and Bryan Counties
- 20.4 miles of new 30-inch-diameter pipeline lateral in Kingfisher County (the Chisholm Lateral)
- 13.6 miles of new 16-inch-diameter pipeline lateral in Stephens, Carter, and Garvin Counties (the Velma Lateral)
- Three new compressor stations and one new booster station in Canadian, Garvin, Bryan, and Stephens Counties
- Seven new receipt meters, two new receipt taps, and four new delivery meters in Bryan, Canadian, Carter, Garvin, Grady, Kingfisher, and Stephens Counties
- Appurtenant facilities
According to the EIS, if the Midship Project is constructed and operated in accordance with applicable laws and regulations, the mitigation measures discussed in the EIS, and FERC’s recommendations, impacts on the environment would be reduced to acceptable levels.
Although many factors were considered, reasons given for this determination include:
- About 128.7 miles (55 percent) of the of the project pipeline facilities would be within or adjacent to existing rights-of-way, consisting of existing pipeline, electric transmission utility (i.e., powerline), and/or road rights-of-way.
- Midship Pipeline would minimize impacts on natural and cultural resources during construction and operation of the project by implementing FERC’s Upland Erosion Control, Revegetation, and Maintenance Plan and Wetland and Waterbody Construction and Mitigation Procedures as well as other project-specific plans (e.g., Fugitive Dust Control Plan, Horizontal Directional Drill Procedures and Mud Monitoring Plan, Migratory Bird Conservation Plan, Unanticipated Discovery Plan, Karst Mitigation Plan, Spill Prevention and Response Procedures, Blasting Plan).
- FERC staff would complete Endangered Species Act consultations with the U.S. Fish and Wildlife Service prior to allowing any construction to begin.
- FERC staff would complete consultation under section 106 of the National Historic Preservation Act and implementing regulations at 36 CFR 800 prior to allowing any construction to begin.
- Midship Pipeline would comply with all applicable air and noise regulatory requirements during construction and operation of the project.
- An environmental inspection program would be implemented to ensure compliance with the mitigation measures that become conditions of the FERC authorization.
The EIS is based on a review of the information provided by Midship Pipeline and further developed from data requests; field investigations; scoping; literature research; alternatives analyses; and contacts with federal, state, and local agencies, Native American tribes, and other stakeholders. It was prepared in compliance with the requirements of the National Environmental Policy Act (NEPA), the Council on Environmental Quality regulations for implementing NEPA (Title 40 of the Code of Federal Regulations [CFR] Parts 1500–1508), and the FERC regulations implementing NEPA (18 CFR 380).
Related News
Related News
- Trump Aims to Revive 1,200-Mile Keystone XL Pipeline Despite Major Challenges
- Valero Considers All Options, Including Sale, for California Refineries Amid Regulatory Pressure
- ConocoPhillips Eyes Sale of $1 Billion Permian Assets Amid Marathon Acquisition
- ONEOK Agrees to Sell Interstate Gas Pipelines to DT Midstream for $1.2 Billion
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- U.S. LNG Export Growth Faces Uncertainty as Trump’s Tariff Proposal Looms, Analysts Say
- Tullow Oil on Track to Deliver $600 Million Free Cash Flow Over Next 2 Years
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- GOP Lawmakers Slam New York for Blocking $500 Million Pipeline Project
- Texas Oil Company Challenges $250 Million Insurance Collateral Demand for Pipeline, Offshore Operations
Comments