Judge Refuses to Delay Hearing on Pipeline Land Acquisition
HARRISONBURG, Va. (AP) — A federal judge has refused to postpone a hearing in a lawsuit brought by developers seeking possession of land in several Virginia counties for a controversial pipeline project.
Atlantic Coast Pipeline is seeking possession of several properties in Augusta, Bath, Buckingham and Cumberland counties for the natural gas pipeline, which would run through West Virginia, Virginia and North Carolina.
The judge declined Monday to postpone a Feb. 26 hearing regarding land in Bath County, but he ordered developers to turn over more information and gave property owners more time to respond. Disputes over land in other counties also will be addressed at next Monday’s hearing.
Developers say federal environmental regulations require completion of any tree felling by March 14, and that missing that deadline would push back construction until November.
Related News
Related News
- Williams' $1 Billion Gas Pipeline Blocked by U.S. Appeals Court, Derailing Five-State Project
- Texas Waha Hub Gas Prices Plunge to Record Lows, Hit Negative Territory
- Williams Begins Louisiana Pipeline Construction Despite Ongoing Legal Dispute with Energy Transfer
- U.S. Buys Nearly 5 Million Barrels of Oil for Emergency Stockpile
- U.S. Appeals Court Strikes Down Controversial Biden Pipeline Safety Rules
- Report: Houston Region Poised to Become a Global Clean Hydrogen Hub
- Exxon Mobil to Start Gas Reserve Seismic Surveys in Greece
- LaPorte, Texas, Issues Shelter in Place After Altivia Plant Leaks Toxic Gas
- Texas Startup Endeavors Again to Build First Major U.S. Oil Refinery Since 1977
- Mid-Year Global Forecast: Midstream Responding to Demand from LNG Projects
Comments