El Paso Natural Gas Files South Mainline Application
5/9/2018
El Paso Natural Gas (EPNG), a wholly-owned subsidiary of Kinder Morgan, has submitted an application to the Federal Energy Regulatory Commission (FERC) seeking authorization to construct and operate the $127.9 million South Mainline Expansion Project, which would expand capacity on the company's Line Nos. 1100 and 1103 by 321,000 Dth/d in Hudspeth and El Paso counties in Texas to serve markets in Texas, New Mexico, Arizona, California and Mexico.
The project, which is expected to be placed in service by July 1, 2020, includes the construction of approximately 17 miles of 30-inch pipeline loop on the existing lines and 13,220 hp turbine-driven compressor stations in Luna County, N.M., and Cochise County, Ariz.
Related News
Related News
Sign up to Receive Our Newsletter
- Phillips 66 to Shut LA Oil Refinery, Ending Major Gasoline Output Amid Supply Concerns
- FERC Sides with Williams in Texas-Louisiana Pipeline Dispute with Energy Transfer
- U.S. Appeals Court Blocks Kinder Morgan’s Tennessee Pipeline Permits
- ConocoPhillips Eyes Sale of $1 Billion Permian Assets Amid Marathon Acquisition
- Valero Considers All Options, Including Sale, for California Refineries Amid Regulatory Pressure
- U.S. Appeals Court Blocks Kinder Morgan’s Tennessee Pipeline Permits
- Malaysia’s Oil Exports to China Surge Amid Broader Import Decline
- U.S. LNG Export Growth Faces Uncertainty as Trump’s Tariff Proposal Looms, Analysts Say
- Marathon Oil to Lay Off Over 500 Texas Workers Ahead of ConocoPhillips Merger
- Valero Considers All Options, Including Sale, for California Refineries Amid Regulatory Pressure
Pipeline Project Spotlight
Owner:
East African Crude Oil Pipeline Company
Project:
East African Crude Oil Pipeline (EACOP)
Type:
TotalEnergies in discussions with a Chinese company after Russian supplier Chelpipe was hit by sanctions.
Length:
902 miles (1,443 km)
Capacity:
200,000 b/d
Start:
2022
Completion:
2025
Comments