El Paso Natural Gas (EPNG), a wholly-owned subsidiary of Kinder Morgan, has submitted an application to the Federal Energy Regulatory Commission (FERC) seeking authorization to construct and operate the $127.9 million South Mainline Expansion Project, which would expand capacity on the company's Line Nos. 1100 and 1103 by 321,000 Dth/d in Hudspeth and El Paso counties in Texas to serve markets in Texas, New Mexico, Arizona, California and Mexico.
The project, which is expected to be placed in service by July 1, 2020, includes the construction of approximately 17 miles of 30-inch pipeline loop on the existing lines and 13,220 hp turbine-driven compressor stations in Luna County, N.M., and Cochise County, Ariz.
Related News
Related News
Sign up to Receive Our Newsletter
- Williams' $1 Billion Gas Pipeline Blocked by U.S. Appeals Court, Derailing Five-State Project
- Texas Waha Hub Gas Prices Plunge to Record Lows, Hit Negative Territory
- Williams Begins Louisiana Pipeline Construction Despite Ongoing Legal Dispute with Energy Transfer
- U.S. Buys Nearly 5 Million Barrels of Oil for Emergency Stockpile
- U.S. Appeals Court Strikes Down Controversial Biden Pipeline Safety Rules
- Report: Houston Region Poised to Become a Global Clean Hydrogen Hub
- Exxon Mobil to Start Gas Reserve Seismic Surveys in Greece
- LaPorte, Texas, Issues Shelter in Place After Altivia Plant Leaks Toxic Gas
- Texas Startup Endeavors Again to Build First Major U.S. Oil Refinery Since 1977
- Mid-Year Global Forecast: Midstream Responding to Demand from LNG Projects
Pipeline Project Spotlight
Owner:
East African Crude Oil Pipeline Company
Project:
East African Crude Oil Pipeline (EACOP)
Type:
TotalEnergies in discussions with a Chinese company after Russian supplier Chelpipe was hit by sanctions.
Length:
902 miles (1,443 km)
Capacity:
200,000 b/d
Start:
2022
Completion:
2025
Comments