Valley Crossing Pipeline to Mexico Gains FERC Extension
The Federal Energy Regulatory Commission (FERC) awarded Enbridge subsidiary Valley Crossing Pipeline six additional months to connect its natural gas pipeline to its counterpart in Mexico, moving the deadline to April 23.

The 168-mile pipeline, expected to have been operational in October, was delayed by rough seas on Mexican side of the project. When completed it will transport 2.6 Bcf/d from the Eagle Ford Shale of South Texas to power plants in Mexico.
From the Agua Dulce natural gas hub outside of Corpus Christi, Texas, the project heads south to the Port of Brownsville, then enters the Gulf of Mexico before crossing the border.
TransCanada is building the underwater pipeline from Tuxpan, Veracruz, which will join the Valley Crossing Pipeline at the border.
Valley Crossing said it is in discussions with a number of potential end users, such as local distribution companies and power plants to install delivery points along the pipeline.
Related News
Related News

- Kinder Morgan Proposes 290-Mile Gas Pipeline Expansion Spanning Three States
- Valero Plans to Shut California Refinery, Takes $1.1 Billion Hit
- Three Killed, Two Injured in Accident at LNG Construction Site in Texas
- Tallgrass to Build New Permian-to-Rockies Pipeline, Targets 2028 Startup with 2.4 Bcf Capacity
- TC Energy Approves $900 Million Northwoods Pipeline Expansion for U.S. Midwest
- U.S. Pipeline Expansion to Add 99 Bcf/d, Mostly for LNG Export, Report Finds
- Enbridge Adds Turboexpanders at Pipeline Sites to Power Data Centers in Canada, Pennsylvania
- Great Basin Gas Expansion Draws Strong Shipper Demand in Northern Nevada
- Cheniere Seeks FERC Approval to Expand Sabine Pass LNG Facility
- Heath Consultants Exits Locate Business to Expand Methane Leak Detection Portfolio
Comments