Exxon OK’s Project to Nearly Double Size of Texas Refinery, Sources Say
1/29/2019
HOUSTON (Reuters) – After agreeing last year to form a joint venture with Plains All American Pipeline to build a 1 MMbpd oil pipeline to refineries in Baytown and Beaumont, Exxon has given final approval to almost double the capacity of its 365,000 bpd Beaumont refinery.
The authorization is the final step to begin building a third crude distillation unit (CDU) that would process between 250,000 bpd and 350,000 bpd of light crude at the refinery located 87 miles (140 km) east of Houston.
With a 250,000 bpd CDU, the plant’s total capacity would reach 615,644 bpd, placing it ahead of the nation’s largest, Motiva Enterprises' 603,000 bpd refinery, in nearby Port Arthur, Texas.
“It has been approved,” said one of the people familiar with the refinery expansion. Employees have been asked to keep the approval confidential, said the person, who could not be identified because of the restrictions.
The company has not publicly disclosed the cost of the expansion, which is part of a $20 billion investment program outlined in 2017 to increase its U.S. Gulf Coast manufacturing over 10 years.
Exxon spokeswoman Sarah Nordin said on Monday she had no updates on the status of the project. In October, she had confirmed that site preparation work had begun in advance of a final decision.
Last October, Exxon has said construction on the project was expected to begin this year after a final investment decision and estimated the work would be completed in 2022.
Exxon aims to triple its daily crude production in the Permian Basin of West Texas and New Mexico to 600,000 boepd by 2025.
Related News
Related News
Sign up to Receive Our Newsletter

- Repsol Ditches Plans to Develop LNG Terminal on Canada’s East Coast
- Kazakh Oil Decouples from Russian Crude But Risk Weighs on Price
- Pipeline Operator TC Energy Says Stress, Weld Fault Caused Keystone Oil Spill
- US to Sell 26 Million Barrels of Oil Reserves As Mandated by Congress
- Ukraine to Jointly Buy Gas with European Union Countries
- Company Cancels Byhalia Connection Pipeline Project
- US Intelligence Suggests Pro-Ukrainian Group Sabotaged Nord Stream Pipelines -NYT
- EIA: US Natural Gas Output to Hit Record High in 2023, Demand to Fall
- US Regulator Orders Lower Pressure on Keystone Pipeline System After Spill
- US Carbon Pipeline Faces Setback as Residents Refuse to Cede Land Rights
Pipeline Project Spotlight
Owner:
East African Crude Oil Pipeline Company
Project:
East African Crude Oil Pipeline (EACOP)
Type:
TotalEnergies in discussions with a Chinese company after Russian supplier Chelpipe was hit by sanctions.
Length:
902 miles (1,443 km)
Capacity:
200,000 b/d
Start:
2022
Completion:
2025