Enbridge Asked to Revise Environmental Impact Statement for Line 3 Replacement Project
(Reuters) — Enbridge Inc needs to add an analysis of potential oil spills into Lake Superior watershed and submit a revised environmental impact statement (EIS) to proceed with its Line 3 pipeline replacement project, a Minnesota regulator said on Tuesday.
The order from the Minnesota Public Utilities Commission comes as the company struggles with delays amid ongoing disputes with regulators. Enbridge has 60 days to submit its revised EIS.
The commission was ordered to revise Enbridge’s EIS for the project in June after a court determined the previous assessment was inadequate.
Line 3, part of Enbridge’s Mainline network that transports western Canadian crude oil to Midwest refineries, is expected to be in service by the second half of 2020 but many oil industry participants are concerned it will be delayed beyond that.
The project would double capacity to 760,000 barrels per day, providing much-needed relief from congestion on existing Canadian pipelines.
Enbridge was also recently ordered to stop its Mainline overhaul plan due to the “perception of abuse of Enbridge’s market power” by the Canadian Energy Regulator.
Related News
Related News

- Kinder Morgan Proposes 290-Mile Gas Pipeline Expansion Spanning Three States
- Enbridge Plans 86-Mile Pipeline Expansion, Bringing 850 Workers to Northern B.C.
- Intensity, Rainbow Energy to Build 344-Mile Gas Pipeline Across North Dakota
- Tallgrass to Build New Permian-to-Rockies Pipeline, Targets 2028 Startup with 2.4 Bcf Capacity
- U.S. Moves to Block Enterprise Products’ Exports to China Over Security Risk
- U.S. Pipeline Expansion to Add 99 Bcf/d, Mostly for LNG Export, Report Finds
- A Systematic Approach To Ensuring Pipeline Integrity
- US Poised to Become Net Exporter of Crude Oil in 2023
- EIG’s MidOcean Energy Acquires 20% Stake in Peru LNG, Including 254-Mile Pipeline
- Enbridge Sells $511 Million Stake in Westcoast Pipeline to Indigenous Alliance
Comments