Traverse City, Mich. (AP) — A Michigan regulatory panel on Tuesday refused to grant quick permission to run a new oil pipeline beneath a channel that connects two of the Great Lakes, deciding instead to conduct a full review.
Enbridge filed an application in April with the Michigan Public Service Commission to relocate a segment of its Line 5 that extends beneath the Straits of Mackinac, which links Lakes Huron and Michigan.
The Canadian energy transport company wants to replace dual pipelines that rest on the lake floor with a new pipe that would be placed in a 4-mile-long (6.4-kilometer-long) tunnel to be drilled in bedrock beneath the waterway.
Enbridge asked the state commission to approve the plan immediately, arguing that the agency in effect had already given permission by allowing the original Line 5 in 1953. But during an online meeting Tuesday, the panel disagreed on a 3-0 vote.
Members concluded that the proposed tunnel pipe “differs substantially” from the twin pipes that were laid 67 years ago, requiring a new easement and a 99-year lease of public trust property.
The project "involves important factual, policy and legal issues best resolved through a proceeding that includes discovery, comprehensive testimony and evidence to provide a robust record,” the commission said in a statement. It scheduled a public hearing for Aug. 24.
Enbridge's argument that the commission didn't need to conduct an extensive study of the plan drew opposition from Michigan Attorney General Dana Nessel and numerous members of the public who submitted written comments and spoke during the online meeting.
Enbridge spokesman Ryan Duffy said Enbridge “respects the Michigan Public Service Commission's decision and we look forward to the next steps in the regulatory process.”
The commission made its decision as Nessel's office and Enbridge prepared to face off in a state courtroom over a judge's temporary order last week to shut down the existing Line 5 pipes because of recently discovered damage to a support anchor.
Circuit Judge James Jamo was scheduled to hear arguments Tuesday on whether to extend the order or allow oil to resume flowing through the pipes.
Line 5 carries about 23 million gallons (87 million liters) of crude oil and natural gas liquids used in propane between Superior, Wisconsin, and Sarnia, Ontario, spanning portions of Michigan's upper and lower peninsulas.
Related News
Related News

- Enbridge Plans 86-Mile Pipeline Expansion, Bringing 850 Workers to Northern B.C.
- Intensity, Rainbow Energy to Build 344-Mile Gas Pipeline Across North Dakota
- U.S. Moves to Block Enterprise Products’ Exports to China Over Security Risk
- 208-Mile Mississippi-to-Alabama Gas Pipeline Moves Into FERC Review
- Court Ruling Allows MVP’s $500 Million Southgate Pipeline Extension to Proceed
- U.S. Pipeline Expansion to Add 99 Bcf/d, Mostly for LNG Export, Report Finds
- A Systematic Approach To Ensuring Pipeline Integrity
- 275-Mile Texas-to-Oklahoma Gas Pipeline Enters Open Season
- LNG Canada Start-Up Fails to Lift Gas Prices Amid Supply Glut
- Kinder Morgan Gas Volumes Climb as Power, LNG Demand Boost Pipeline Business
Comments