Pennsylvania Orders Sunoco to Reroute Section of Mariner East 2 Pipeline
(Reuters) — Pennsylvania environmental regulators ordered Energy Transfer LP's Sunoco Pipeline unit to reroute a section of the Mariner East 2 natural gas liquids pipeline after spilling 8,000 gallons of drilling fluid in Marsh Creek State Park in August.
Analysts at Height Capital Markets said on Monday the reroute could delay an upgrade to the already operating Mariner East 2 project that was expected to be completed in the second quarter of 2021.
Officials at Energy Transfer were not immediately available for comment.
The Pennsylvania Department of Environmental Protection said late Friday the Marsh Creek spill caused the park to close 33 acres (13 hectares) of the lake from boating and other recreational uses.
"These incidents are yet another instance where Sunoco has blatantly disregarded the citizens and resources of Chester County with careless actions while installing the Mariner East II Pipeline," DEP Secretary Patrick McDonnell said in a statement.
The reroute order was the latest in a long series of sanctions against the company for violations of its permits during construction of Mariner East 2.
Since May 2017, Pennsylvania has issued 115 notices of violation to Mariner East, mostly for drilling fluid spills, including one in September.
Pennsylvania has fined the company and stopped construction on the pipeline several times. Several politicians and local groups have long urged the state to stop work again and shut the pipeline.
Mariner East transports liquids from the Marcellus and Utica shale in western Pennsylvania to customers in the state and elsewhere, including international exports from Energy Transfer's Marcus Hook complex near Philadelphia.
Sunoco started work on the $2.5 billion Mariner East expansion in February 2017 and had planned to finish the 350-mile (563-km) pipeline in the third quarter of 2017.
But completion was delayed until December 2018 due to several work stoppages by state agencies.
Related News
Related News
![](/media/2035/pgj-enews-graphic-300x1404.jpg)
- Mexican President: Billionaire Slim Interested in Pemex Natural Gas Project
- Freeport LNG Sues Three Contractors Over Defects at Texas Plant
- Energy Transfer Adds 6,000 Miles of Pipeline with $3.25 Billion WTG Midstream Acquisition
- FERC Approves Transco's Texas to Louisiana Gas Pipeline Project
- Williams Says Court Rules in Its Favor in Pipeline Dispute with Energy Transfer
- U.S. to Buy 4.5 Million Barrels of Oil to Replenish Strategic Petroleum Reserve
- Kurdish Oil Smuggling to Iran Flourishes
- U.S. Court Overturns Alaska Oil Lease Sale, Halting Energy Development
- Second Gas Pipeline Rupture in Texas’ Reeves County Raises Environmental Concerns
- Williams Begins Louisiana Pipeline Construction Despite Ongoing Legal Dispute with Energy Transfer