Shell Prelude LNG Loading Disrupted Until At Least Mid-July, Worsening Global Supply
(Reuters) — Shell Plc said on Wednesday liquefied natural gas (LNG) shipments from its Prelude floating facility off northwest Australia would be disrupted for at least two weeks due to work bans by unions fighting for better pay.
Loading disruption at the 3.6-million-tonnes-a-year facility adds to tightness in a global LNG market just as Europe scrambles to secure cargoes to make up for lost Russian gas supply. One of the largest U.S. LNG plants, Freeport LNG is also undergoing an extended outage.
"We have issued a notice to customers that cargoes will be impacted until at least mid-July due to the industrial action," a Shell spokesperson said in an emailed comment.
The last cargo left Prelude on June 26 on the ship Oceanic Breeze, Refinitiv data shows.
When operating normally, the site typically loads a tanker every seven to 10 days, which suggests that loading of at least two cargoes will be prevented during the industrial action.
Prelude's loading delays come just three months after the facility resumed shipping LNG following a four-month shutdown due to a major power failure.
Workers on Prelude began 12 days of industrial action on June 10 over a pay dispute. The action has now been extended to July 14, Shell and the Australian Workers' Union said.
Shell has scheduled a vote on a new offer, including an increase of A$27,000 in the offshore allowance to A$117,000 ($80,900) a year, an increase of A$3,000 in the commuting allowance to A$10,000 annually, and other benefits.
The Australian Workers' Union says Shell has yet to meet some of its demands, including one that would stop Shell from hiring contract workers at lower pay than the company's employees doing the same job.
Prelude is co-owned by Shell, Inpex Corp., Korea Gas Corp. (KOGAS), and a subsidiary of Taiwan's state-run Chinese Petroleum Corp. Shell operates the facility.
($1 = 1.4459 Australian dollars)
Related News
Related News
- Trump Aims to Revive 1,200-Mile Keystone XL Pipeline Despite Major Challenges
- ONEOK Agrees to Sell Interstate Gas Pipelines to DT Midstream for $1.2 Billion
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- Boardwalk Approves 110-Mile, 1.16 Bcf/d Mississippi Kosci Junction Pipeline Project
- Energy Transfer Receives 16 Bcf/d Natural Gas Requests Amid Growing Data Center, Power Needs
- Tullow Oil on Track to Deliver $600 Million Free Cash Flow Over Next 2 Years
- GOP Lawmakers Slam New York for Blocking $500 Million Pipeline Project
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- Polish Pipeline Operator Offers Firm Capacity to Transport Gas to Ukraine in 2025
- Macquarie, Dow Launch $2.4 Billion Gulf Coast Pipeline Infrastructure Partnership
Comments