Caspian Pipeline Consortium Resumes Oil Loadings at Black Sea Terminal
(Reuters) — The Caspian Pipeline Consortium (CPC), a main export route for Kazakhstan's crude oil, said on Thursday it has resumed oil loadings at its Black Sea terminal which had been suspended due to storms, disrupting exports since last Friday.
It said one of three single point moorings (SPM) at the terminal had been damaged, and oil was being loaded via SPM 1 and SPM 2. Malfunctioning SPMs also led to oil export disruption from CPC's Black Sea terminal last year.
Oil exports via CPC are expected to rise in December to 5.6 million metric tons from 5.4 million tons in the November plan, said three traders familiar with the export plan.
Russia exports its oil from the Black Sea terminal of Sheskharis, near Novorossiisk, while CPC, handling around 1% of global oil, ships oil from the nearby terminal of Yuzhnaya Ozereevka.
It was not immediately clear if supplies via Sheskharis have also been resumed.
Severe storms in the Black Sea region have disrupted up to 2 million barrels per day (bpd) of oil exports from Kazakhstan and Russia since last Friday.
"In the northern part of the Black Sea, unfavorable hydrometeorological conditions remain. In this regard, navigation restrictions continue to apply in the main seaports of Russia in the Black Sea basin until the weather improves," the ministry of transport said earlier on Thursday.
Separately, the Russian Federal Agency for Sea and Inland Water Transport (Rosmorrechflot) said that ferries across the Kerch Strait, which separates Russia from Crimea at the mouth of the Azov Sea, had resumed operations on Thursday morning.
Black Sea terminals, including the ports of Novorossiisk and Taman, also handle about 70% of Russia's grain exports.
Kazakhstan's three largest oilfields cut their combined daily output by 103,800 metric tons on Wednesday because of the disruption to shipping in the Black Sea, according to the energy ministry.
Production was down 67% at the Tengiz field, 65% at the Kashagan field and 34% at the Karachaganak field, the ministry said in a statement on Thursday.
Related News
Related News
- Trump Aims to Revive 1,200-Mile Keystone XL Pipeline Despite Major Challenges
- $3 Billion Natural Gas Pipeline Expansion to Add 1.3 Bcf Capacity in Southeast Region
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- Boardwalk Approves 110-Mile, 1.16 Bcf/d Mississippi Kosci Junction Pipeline Project
- Kinder Morgan Approves $1.4 Billion Mississippi Crossing Project to Boost Southeast Gas Supply
- Tullow Oil on Track to Deliver $600 Million Free Cash Flow Over Next 2 Years
- GOP Lawmakers Slam New York for Blocking $500 Million Pipeline Project
- Enbridge Should Rethink Old, Troubled Line 5 Pipeline, IEEFA Says
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- Polish Pipeline Operator Offers Firm Capacity to Transport Gas to Ukraine in 2025
Comments