Exxon to Complete Beaumont, Texas, Hydrocracker Overhaul by End of March, Sources Say
(Reuters) — Exxon Mobil Corp. plans to finish an overhaul of the hydrocracker at its 619,024 barrel-per-day (bpd) Beaumont, Texas refinery by the end of March, said people familiar with plant operations on Monday.
The 60,000-bpd hydrocracker was shut on March 1 for the planned overhaul, the two sources said. The 80,000-bpd PTR-4 catalytic reformer is also shut for work.
Exxon spokesperson Lauren Kight declined on Monday to discuss operations at the Beaumont refinery.
Exxon also plans to shut the 35,000-bpd CHD-1 hydrotreater for two weeks of work in April, according to the sources.
Hydrocrackers use high heat and pressure in the presence of hydrogen to convert gas oil into diesel and other motor fuels.
Reformers convert refining byproducts into octane-boosting components to make premium grades of gasoline.
Hydrotreaters use hydrogen to remove sulfur from motor fuels to comply with U.S. environmental rules.
Related News
Related News

- Kinder Morgan Proposes 290-Mile Gas Pipeline Expansion Spanning Three States
- Valero Plans to Shut California Refinery, Takes $1.1 Billion Hit
- Three Killed, Two Injured in Accident at LNG Construction Site in Texas
- Tallgrass to Build New Permian-to-Rockies Pipeline, Targets 2028 Startup with 2.4 Bcf Capacity
- TC Energy Approves $900 Million Northwoods Pipeline Expansion for U.S. Midwest
- New Alternatives for Noise Reduction in Gas Pipelines
- EIG’s MidOcean Energy Acquires 20% Stake in Peru LNG, Including 254-Mile Pipeline
- Construction Begins on Ghana's $12 Billion Petroleum Hub, But Not Without Doubts
- DOE Considers Cutting Over $1.2 Billion in Carbon Capture Project Funding
- Valero Plans to Shut California Refinery, Takes $1.1 Billion Hit
Comments