Exxon to Complete Beaumont, Texas, Hydrocracker Overhaul by End of March, Sources Say
(Reuters) — Exxon Mobil Corp. plans to finish an overhaul of the hydrocracker at its 619,024 barrel-per-day (bpd) Beaumont, Texas refinery by the end of March, said people familiar with plant operations on Monday.
The 60,000-bpd hydrocracker was shut on March 1 for the planned overhaul, the two sources said. The 80,000-bpd PTR-4 catalytic reformer is also shut for work.
Exxon spokesperson Lauren Kight declined on Monday to discuss operations at the Beaumont refinery.
Exxon also plans to shut the 35,000-bpd CHD-1 hydrotreater for two weeks of work in April, according to the sources.
Hydrocrackers use high heat and pressure in the presence of hydrogen to convert gas oil into diesel and other motor fuels.
Reformers convert refining byproducts into octane-boosting components to make premium grades of gasoline.
Hydrotreaters use hydrogen to remove sulfur from motor fuels to comply with U.S. environmental rules.
Related News
Related News
- Trump Aims to Revive 1,200-Mile Keystone XL Pipeline Despite Major Challenges
- Valero Considers All Options, Including Sale, for California Refineries Amid Regulatory Pressure
- ConocoPhillips Eyes Sale of $1 Billion Permian Assets Amid Marathon Acquisition
- ONEOK Agrees to Sell Interstate Gas Pipelines to DT Midstream for $1.2 Billion
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- U.S. LNG Export Growth Faces Uncertainty as Trump’s Tariff Proposal Looms, Analysts Say
- Tullow Oil on Track to Deliver $600 Million Free Cash Flow Over Next 2 Years
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- GOP Lawmakers Slam New York for Blocking $500 Million Pipeline Project
- Texas Oil Company Challenges $250 Million Insurance Collateral Demand for Pipeline, Offshore Operations
Comments