Shell, Edison Urge U.S. Regulators to Reject Venture Global LNG's Permit Extension Request
3/8/2024
(Reuters) — Italian utility Edison and Shell on Friday asked U.S. energy regulators to reject Venture Global LNG's request for a one-year construction permit extension to its Louisiana export plant.
Edison also asked the Federal Energy Regulatory Commission to compel Venture Global to release commissioning documents to justify the extension request.
"Shell LNG respectfully requests that the Commission find the Extension Request, in its conditional form, to be moot and summarily deny it," the company said.
Venture Global last month asked for a one-year extension to a Federal Energy Regulatory Commission (FERC) permit to complete its Calcasieu Pass plant, or to receive assurances it did not need an extension.
Related News
Related News
Sign up to Receive Our Newsletter

- 1,000-Mile Pipeline Exit Plan by Hope Gas Alarms West Virginia Producers
- Valero Plans to Shut California Refinery, Takes $1.1 Billion Hit
- Three Killed, Two Injured in Accident at LNG Construction Site in Texas
- Greenpeace Ordered to Pay $667 Million to Energy Transfer Over Dakota Access Pipeline Protests
- Boardwalk’s Texas Gas Launches Open Season for 2 Bcf/d Marcellus-to-Louisiana Pipeline Expansion
- New Alternatives for Noise Reduction in Gas Pipelines
- Construction Begins on Ghana's $12 Billion Petroleum Hub, But Not Without Doubts
- Missouri Loses Control Over 1.5 Million-Mile Gas Pipeline Network as Feds Step In
- Gazprom’s Grandeur Fades as Europe Moves Away from Russian Gas
- Greenpeace Ordered to Pay $667 Million to Energy Transfer Over Dakota Access Pipeline Protests
Pipeline Project Spotlight
Owner:
East African Crude Oil Pipeline Company
Project:
East African Crude Oil Pipeline (EACOP)
Type:
TotalEnergies in discussions with a Chinese company after Russian supplier Chelpipe was hit by sanctions.
Length:
902 miles (1,443 km)
Capacity:
200,000 b/d
Start:
2022
Completion:
2025
Comments