August 2016, Vol. 243, No. 8

Features

Gas Flows to Millions in Thailand While Pipeline Repaired

The pressure isolation operation in Thailand required the use of a SmartPlug tool.

Responsible for providing Thailand with 20% of its natural gas supply, PTT Exploration and Production Public Company Limited (PTTEP) work to make sure natural gas production from the Bongkot and Erawan production platforms, located in the Gulf of Thailand, flow with little disruption.

Since replacing valves is a routine function in pipeline maintenance, the PTTEP team responded quickly when it identified three topside valves needed replacing on the gas export riser attached to the Bongkot platform.

The Bongkot platform is connected to a major export line that extends to the Erawan production platform, a primary hub of gas production in Thailand, through which millions of cubic feet of natural gas are transported daily to the onshore processing plant in Rayong.

PTTEP partnered with global pipeline service provider T.D. Williamson (TDW) to isolate pressure in the pipeline from the work zone and depressurize the affected section. By doing so, a safe working environment was created in which the contractor could replace the defective valves.

PTTEP opted for the isolation method to avoid the downtime, expense and disruption of bleeding the entire line. The objective was to keep interruption to gas production to a minimum: no more than 10 days.

Following months of pre-engineering work and preparation, the TDW team deployed a triple-module 32-inch SmartPlug® pressure isolation tool. The configuration featured two modules for isolating the pipeline inventory during the valve replacement works, and a third plug module to act as barrier for post-repair hydrostatic testing.

The system achieved a double-block isolation against gas pressure in the pipeline. The SmartPlug system is characterized as double-block because the two plug modules act independently from one another, thereby satisfying the requirement for double isolation, as required by Det Norske Veritas (DNV) and other regulatory bodies.

Working from the Bongkot platform, TDW launched the SmartPlug tool into the line, pigging it in potable water about 40 meters past the hanger flange and into the vertical set location in the riser. As it traveled through the line, TDW tracked the tool’s progress with its remotely operated SmartTrack™ tracking and monitoring system, which uses extremely low-frequency (ELF) signals.

The system also monitors pressure between the two plug modules to ensure it remained at a safe operating level throughout the isolation operation. Tracking and monitoring were achieved by the two-way, through-wall, electromagnetic communication capability between an external transponder and the receiver in the tool. Upon setting the isolation tool at the pre-determined destination, it was sealed against a safe operating pressure of about 100 bar (1,450 psi) for 10 days.

The two valves were replaced during the isolation period, after which TDW carried out a hydrotest to a pressure of 132 bar (1,930 psi) against the tool’s third plug module to verify the integrity.

With the hydrotest complete and the integrity of the repair work verified, PTTEP was satisfied that the valves had been repaired. The pressure over the SmartPlug tool was then equalized, the plug modules unset and the tool pigged back to the launcher using the gas pressure from the pipeline. Finally, the pressure was bled at the launcher side.

“When we completed the 32-inch Bongkot valve replacement and riser wrapping project in late April 2014, gas export had already resumed,” said a division manager for PTT.

By employing the pipeline pressure-isolation method for the Bongkot-Erawan pipeline repair program, PTTEP realized a number of benefits.

“This field-proven technology allows maintenance to be carried out without blowing down or depressurizing the pipeline, each of which is a very complex, time-consuming and expensive process,” said Rolf Gunnar Lie, regional business development manager. “The fact that the downstream sections of the repair zone can be isolated, with just the repair zone depressurized, is extremely important because repair work can be completed safely, with minimal disruption to production.”

 

Related Articles

Comments

{{ error }}
{{ comment.comment.Name }} • {{ comment.timeAgo }}
{{ comment.comment.Text }}