Enbridge Completes Rock Sampling for Michigan Tunnel Project
TRAVERSE CITY, Mich. (AP) — Enbridge says it has completed sediment and rock sampling in preparation for building a Michigan oil pipeline tunnel under the Great Lakes.
The Canadian company said Thursday its crews took core samples from 27 locations in the Straits of Mackinac area, where Lakes Huron and Michigan meet.
Project manager Amber Pastoor said geologists will study the samples. Results will be used to design the tunnel and a machine to drill through bedrock beneath the lake floor.
Enbridge negotiated an agreement with former Republican Gov. Rick Snyder to run an oil pipe through the tunnel and shut down its twin Line 5 pipes that traverse the lake bottom.
His Democratic successor, Gretchen Whitmer, opposes the deal. Attorney General Dana Nessel is appealing a court ruling that upheld legislation authorizing the agreement.
Nessel also has filed a lawsuit to decommission Line 5.
Related News
Related News

- Intensity, Rainbow Energy to Build 344-Mile Gas Pipeline Across North Dakota
- Energy Transfer to Build $5.3 Billion Permian Gas Pipeline to Supply Southwest
- Enbridge Sees High Demand to Expand 593-Mile Canada-to-U.S. Gulf Oil Pipeline
- Strike Pioneers First-of-Its-Kind Pipe-in-Pipe Installation on Gulf Coast with Enbridge
- 208-Mile Mississippi-to-Alabama Gas Pipeline Moves Into FERC Review
- A Systematic Approach To Ensuring Pipeline Integrity
- 275-Mile Texas-to-Oklahoma Gas Pipeline Enters Open Season
- LNG Canada Start-Up Fails to Lift Gas Prices Amid Supply Glut
- Strike Pioneers First-of-Its-Kind Pipe-in-Pipe Installation on Gulf Coast with Enbridge
- Enbridge Sees High Demand to Expand 593-Mile Canada-to-U.S. Gulf Oil Pipeline
Comments